Skip to main content
 
File #: 24-3214    Version: 1
Status: Agenda Ready
File created: 10/18/2024 In control: Board of Public Utilities
On agenda: 11/18/2024
Title: Approve Services Agreement to Request for Proposal 2357 with GE Vernova Operations, LLC., Houston, Texas, for $804,113.70 to perform Inlet Guide Vane upgrades on gas turbines at Springs Power Plant - Approve Work Order 2505220 including 10 percent contingency of $80,411.37 for total amount of $884,525.07 from Public Utilities Capital Account
Attachments: 1. Report, 2. RFP Award Recommendation, 3. Agreement, 4. Presentation