Title:
|
Award RPU Bid 8078 to Herman Weissker, Inc., in amount of $3,661,859.05 - Authorize including change order authority in not-to-exceed amount of 10 percent or $366,185.91 - Approve capital expenditure for Work Order 2208638 in amount of $4,200,000 from Public Utilities’ Electric Capital Account to include design, construction, construction support, contract administration, inspection and construction change order authority costs - Streetlight Replacement Project, Phase 5
|