Title: Award Bid SUB-875 for procurement of one substation power transformer to WEG Transformers USA, LLC, Washington, Missouri, in amount of $3,124,956 - Approve 25 percent contingency of $781,149 for Bid SUB-875 - Award Bid SUB-876 for procurement of one 15KV Metalclad Switchgear to Switchgear Power Systems, LLC, Winneconne, Wisconsin, in amount of $2,254,388 - Approve 20 percent contingency of $450,507 for Bid SUB-876 - Approve increase to Work Order 2202776 in amount of $6,611,000, for total Work Order amount from $7,080,000 to $13,691,000 from Public Utilities Substation Transformer Upgrade Capital Account
Attachments: 1. Report, 2. Project Site Map, 3. Bid No. 876 Award Recommendation, 4. Bid No. 875 Award Recommendation, 5. Presentation