Legislation Details

File #: 26-3500    Version: 1
Status: Agenda Ready
File created: 10/15/2026 In control: Board of Public Utilities
On agenda: 11/9/2026
Title: Reject bid submitted by Servitek Electric, Inc., Norwalk, as non-responsive - Award Bid 8273 to International Line Builders, Inc., Corona, for $934,383.27 for Hunter Substation Circuits 21 and 22 4kV to 12kV Make-Ready Project, Phase 2 - Approve Work Order 2614695 for total capital expenditure of $2,204,845.99 from Public Utilities Electric Fund Capital Account for design, construction, construction support, contract administration, inspection, and construction change order authority costs for Hunter Substation Circuits 21 and 22 4kV to 12kV Make-Ready Project, Phase 2
Attachments: 1. Report, 2. Project Site Map, 3. Bid Award Recommendation, 4. Presentation