File #: 17-1057    Version: 1
Status: Agenda Ready
File created: 3/21/2017 In control: Board of Public Utilities
On agenda: 4/10/2017
Title: CONSTRUCTION OF THE MAGNOLIA AVENUE AND RAMONA DRIVE WATER DISTRIBUTION MAIN REPLACEMENT PROJECT – AWARD OF BID NO. RPU-7464 TO SULLY-MILLER CONTRACTING CO. OF BREA, CALIFORNIA, IN THE AMOUNT OF $1,984,777 – APPROVE WORK ORDER NO. 1107917 FOR $2,704,000 That the Board of Public Utilities: 1. Award a contract for the construction of the Magnolia Avenue and Ramona Drive Water Distribution Main Replacement Project – Bid No. RPU-7464 to the lowest responsive and responsible bidder, Sully-Miller Contracting Co. of Brea, California, in the amount of $1,984,777; and 2. Approve the capital expenditure of $2,704,000 for Work Order No. 1107917, which includes all design, construction, paving, contract administration, inspection and construction contingency costs for the Magnolia Avenue and Ramona Drive Water Distribution Main Replacement Project.
Attachments: 1. Report, 2. Bid Award, 3. Presentation