Title:
|
Increase change order for Bid DSM003 with SAK Construction, LLC, to 20% for $834,096 for total contract of $5,004,576 for accelerated bypass system installation, surge tank procurement and installation, potential project delay, and future unanticipated work for sewer force main rehabilitation completion - Transfer $1,900,000 from Ninth Street Sewer Replacement Project to Trautwein and Alessandro Sewer Force Main Emergency Rehabilitation Project Account (Ward 4)
|