Title:
|
Award Bid SUB-865 to Concept Power Inc., Las Vegas, Nevada, for $78,849.30 from Public Utilities Substation Bus Upgrade Account to furnish flooded battery bank - Approve capital expenditure for Work Order 2311734 in the amount of $108,000 for design, construction, procurement, testing and commissioning and construction support for Riverside Substation Battery Replacement Project
|
Indexes:
|
CCT – Community Trust, CCT – Equity, CCT – Fiscal Responsibility, CCT – Innovation, CCT – Sustainability & Resiliency, SP 6 – Infrastructure, Mobility & Connectivity, Strategic Goal 6.2, Ward 2
|
Attachments:
|
1. Report, 2. Map, 3. Presentation
|