Title: Approve capital expenditure for Work Order 2312723 in the amount of $275,000 from Public Utilities Substation Bus Upgrade Account for design, construction, procurement, testing, commissioning, and construction support to upgrade 66kV bus differential protection system and remove Transformer T4 and Switchgear No. 4 at Plaza Substation