Please note: this meeting's minutes have not been finalized yet. Actions taken on legislation and their results are not available.
Meeting Name: Board of Public Utilities Agenda status: Final
Meeting date/time: 11/18/2024 6:30 PM Minutes status: Draft  
Meeting location: City Hall - Art Pick Council Chamber 3900 Main Street, Riverside Live Webcast at: www.RiversideCA.gov/Meeting
Special Meeting
Published agenda: Agenda Agenda Accessible Agenda Accessible Agenda Published minutes: Not available Meeting Extra1: Not available  
Meeting video: eComment: Not available  
Attachments:
File #Agenda #TitleVideo
24-3143 1To comment on any matters within the jurisdiction of the Board of Public Utilities, you are invited to participate via telephone at (951) 826-8688. Press *9 to be placed in the queue to speak. Individuals in the queue will be prompted to unmute by pressing *6 when you are ready to speak. To participate via ZOOM, use the following link: https://zoom.us/j/92696991265, select the "raise hand" function to request to speak. An on-screen message will prompt you to "unmute" and speak. Not available
24-3205 2Riverside Public Utilities sustainability efforts Not available
24-3144 3Declaration of conflicts of interest on any agenda items (Board of Public Utilities) Not available
24-3230 4Minutes of October 28, 2024 Not available
24-3210 5Approve Service Agreement for Bid 8079 with Inland Electric Inc., Riverside, for $213,997 for replacement of one standby generator per site at Box Springs, Orange Terrace, and Tilden radio sites - Approve capital expenditure for Work Order 2311805 in amount of $271,000 from Public Utilities Electric Capital Account for three (3) Radio Sites Standby Generator Replacement Project Not available
24-3211 6Increase to Purchase Order 252027 with Herman Weissker, Inc., for total amount of $44,866 - Approve increase to Work Order 2501500 in amount of $31,953 for total capital expenditure of $60,000 from Public Utilities Electric Capital Account for cable replacement - Arroyo Drive Not available
24-3212 7Increase to Purchase Order 250243 with Trane U.S. Inc., for $45,749 for revised total of $122,254 from Public Utilities Maintenance Generating Plants Account for as needed repairs on air inlet chillers for 2024-2025 fiscal year - Riverside Energy Resource Center Not available
24-3304 8Board of Public Utilities recommend City Council approve legal budget in amount not to exceed $600,000 from the PU Elec Power Supply Operation-Outside Legal Services Account for law firm of Thompson Coburn to initiate petition with Federal Energy Regulatory Commission regarding City’s Transmission Revenue Requirement Not available
24-3213 9Award Bid 8117 to Asplundh Construction, LLC., Anaheim, for $6,452,235 for construction of 69kV Riverside Energy Resource Center (RERC) to Freeman sub-transmission line - Authorize 20 percent contingency in amount of $1,290,447 and authorize staff to issue change orders to construction contract - Approve Work Order 2117652 for total capital expenditure of $8,342,682 from Public Utilities Electrical Capital Account for purpose of tracking work related to construction of 69kV RERC to Freeman line as part of Riverside Transmission Reliability Project Work Order 642975 Not available
24-3214 10Approve Services Agreement to Request for Proposal 2357 with GE Vernova Operations, LLC., Houston, Texas, for $804,113.70 to perform Inlet Guide Vane upgrades on gas turbines at Springs Power Plant - Approve Work Order 2505220 including 10 percent contingency of $80,411.37 for total amount of $884,525.07 from Public Utilities Capital Account Not available
24-3197 11Systematic reporting on meetings, conferences, and seminars by Board members and/or staff Not available
24-3196 12Items for future Board of Public Utilities consideration as requested by members of the Board. Only items that fall within the powers and duties of the Board of Public Utilities as set forth in the City Charter and/or the Riverside Municipal Code will be agendized for future discussion. Not available
24-3208 13WA-12 Agricultural Service Water Rate Report as of September 30, 2024 Not available
24-3199 14Accounts Receivable and Delinquencies as of September 30, 2024 Not available
24-3209 15Customer Engagement Report updates through September 2024 Not available
24-3200 16Power Supply Report - September 2024 Not available
24-3201 17Water Supply Report - September 2024 Not available
24-3198 18Electric and Water Open Work Orders over $200,000 and Closed Work Orders Summary Reports for September 2024 Not available
24-3202 19Electric and Water Contractor and Consultant Panel updates for September 2024 Not available
24-3203 20Upcoming City Council and Board Meetings Not available
24-3204 21Electric/Water Utility Acronyms Not available