Title:
|
Bid No. SUB-806 for furnishing and delivering a Combined Metal-Cad Switchgear Enclosure to Crown Technical Systems in the amount of $1,343,878.13; Award Bid No. SUB-793 for furnishing and delivering protective relay panels to Keystone Manufacturing Company in the amount of $53,576.17 – Approve Work Order No. 1810532 for Freeman Switchgear and Transformer Upgrade Project for $5,463,000 - (presentation by George Hanson – 5 min)
|